Summary of recent chronology :
April 2011


19/04/2011: Opening the construction site

06/15/2011: Call for tender for general contractor (GC)

05/07/2011: Signing of the Convention CUG - Association of neighbors of the Tavan Road
August 2011

21/07/2011: Answers to GC

22/08/2011: Start of excavation by Grisoni-Zaugg


23/09/2011: Deadline for return of tenders general contractors

27/09/2011: Opening of tenders general contractors
October 2011

09/28/2011: End excavation work phase 1 (Grisoni-Zaugg)

13/10/2011: Hearing of general contractors

20/10/2011: Choice of Implenia General Contractor Ltd.

07/12/2011: Public meeting with FRAR and ImpleniaSite board
 
29/02/2012 : Installation site board
 
08/03/2012 : Geotechnical measurements along Edouard-Tavan road
 
12/03/2012 : locker room roof destruction
 
Locker room roof destruction
19/03/2012 : Begining of structural work (installation of Girsoni-Zaugg)